wall, the beam was lifted and copper flashing was installed to allow the block to sit on the pilaster, safely away from rot and insects. The installation of all 120 SmartJacks™ was completed in less than one week and effectively stabilized and lifted the sagging beams throughout the crawlspaces. Drywall in the units above were repaired for the last time, and cabinets and windows began to open and close properly. All floors throughout the complex are now level with the bowing and bouncing completely eliminated. "I have lived here for several years. The floors bounced so much I started to think I lived on a ship! The day Quality 1st finished the work in my home I thought I was in a new place." -Condominium Unit Owner
Project Summary
Installing Contractor: Quality 1st Basement Systems, Perth Amboy, NJ
Project Engineer: Kipcon Engineering
Quality 1st Certified Inspector: Victor Leon
Products Installed: (120) Foundation Supportworks SmartJacks™